Step 2: Scope & Methodology

Step 2: Scope & Methodology

Before building the schedule, you must understand the full scope of work and the delivery methodology. This step ensures the schedule reflects reality — not just a generic template applied to the project.

Determining the Scope of Work

The project's scope of work can be determined by:

  • Reviewing relevant documents — drawings and plans, technical requirements, functional specifications, etc.
  • Discussing the extent of work with the project team.
  • Comparing the project to similar projects and benchmark data.

Project Phases & Stages

Project stages for infrastructure projects typically include:

  • Project management and Client's activities.
  • Interfaces, agreements, and approvals with external parties.
  • Design development, reviews, and approvals.
  • Procurement of subcontractors, long lead-time materials, and equipment.
  • Off-site fabrication, storage, and delivery.
  • Construction and installation.
  • Testing, commissioning, systems integration, operational readiness, and handover.

Unique & Unusual Project Characteristics

Check if there is anything unusual or unique about the project that could affect the program, including:

  • Unique design.
  • Restricted operating environment — e.g. maintaining existing operations in and around new construction.
  • Restriction on working hours — e.g. night shifts, shutdowns.
  • Restricted access to work site — e.g. rail corridor, motorways.
  • Interfaces with external parties — e.g. utility providers.
  • High degree of complexity.
  • Contract-defined constraints — e.g. separable portions and sequential handovers.

Type of Delivery Contract

The contract type shapes the planning approach, responsibilities, and risk allocation. Common types include:

  • Supply only
  • Design & Construct (D&C)
  • PPP — Public Private Partnership
  • Alliance
  • Incentivised Target
Key principle:

A thorough scope and methodology review upfront prevents costly re-work and re-sequencing later. The more you understand before entering data, the more accurate and credible the schedule will be.