Calendars define the available working time for activities in the schedule. Getting calendars right is essential — errors here ripple through every date calculation in the program.
| Calendar Type | Work Week | Hours/Day | Non-Working Time |
|---|---|---|---|
| Office-based work Design & Procurement |
5-day week | 8 hours | Public holidays, 2-week Christmas break |
| Construction & Installation | 5-day or 6-day week | 8 hours | Public holidays, RDOs, 2-week Christmas break |
| Occupations & Closures Curing, rail possessions |
7-day week | 8 hours | No non-working time |
Detailed railway occupation schedules (hour by hour) should always be maintained in separate schedules outside of the master schedule. Mixing them into the master schedule introduces calendar complexity that can cause significant scheduling errors.
Set up and verify all calendars before entering a single activity. A calendar error discovered late in schedule development can require significant rework to correct across the entire program.